| Hazardous Site Remediation
- Managed the sampling, classification and disposal of over
400 drums of residual and hazardous waste liquids and solids.
This emergency response cleanup was completed in two weeks
so that a prearranged auction of the property could take place
as scheduled. Site remediation consisted of consolidation
and field classification of numerous drums and containers,
lab packing of miscellaneous chemicals, cleanup of a 150 foot
long paint stripping line, spill contaminated soils, empty
containers, and the recycling of selected wastes to minimize
cleanup costs.
Residential Heating Oil Spill - A heating
oil tank burst in the basement of a twin home destroyed by
fire. AA&E conducted a site characterization to determine
the extent of contamination beneath the basement slab. The
remedial design/feasibility study (RI/FS) for this site included
a vapor extraction test and analysis of the native soil to
determine nutrient conditions. An in-situ remedial process
was chosen based on the RI/FS that utilized a combination
of bioremediation and vacuum enhanced recovery as the most
cost-effective remedial alternative. Remedial goals were achieved
without disturbing the basement structure, and the home was
subsequently rebuilt on the original foundation.
Act 2 relief from liability was obtained for this project.
As a result, the owner was able to maintain the value of his
land and pass a clear title to his property.
Landfill Abatement/Groundwater - Completed
and certified geologic and hydrogeologic portions of the closure
permit for a 52-acre sanitary landfill, including a groundwater
contamination assessment and abatement plan addressing leachate
migration from an unlined cell. The primary fracture system
carrying leachate was located by geophysical methods. Remediation
consisted of sealing the fracture system with high-pressure
grout to form a grout curtain, and the installation of groundwater
recovery wells to control the hydraulic gradient. The state
approved plan was implemented as part of the approved closure
permit.
Abandoned Factory - Completed the cleanup
and closure of a meat processing plant for the owner as a
condition of sale. Closure activities included the sampling,
classification and disposal of approximately 80 drums of chemical
liquids, thirty tons of wastewater treatment chemicals, the
removal of four underground storage tanks, the identification
of asbestos containing building material, the sampling of
transformers for PCB content, the remediation of contaminated
soils, and the removal of debris from the site.
Printing Facility - Completed the cleanup
and closure of a printing facility to prepare the property
for sale. Closure activities included the sampling, classification
and disposal of approximately 60 drums of chemical liquids,
the delineation of PCB floor staining, the remediation of
contaminated soils and gross floor staining, and the removal
of debris from the site.
Closed Industrial Site - Completed the
cleanup and disposal of 520 drums of waste material stockpiled
at a closed site. The drums were characterized into eleven
different waste streams and consolidated to minimize disposal
costs. Bulk disposal was arranged for some of the waste, while
the drum streams were sent to three different disposal facilities.
The characterization and consolidation of the waste material
prior to off-site disposal minimizes the cost for the client.
Residential Heating Oil Spill – The
filter casing for a heating oil tank supply line leaked the
contents of the tank onto the basement floor, and AA&E
was asked to determine the extent of contamination beneath
the basement slab and verify that the cleanup had been done
correctly. The remedial design/feasibility study (RI/FS) for
this site included removal of the basement slab, and excavation
of the accessible soil for off-site disposal. Attainment sampling
showed contamination remained at the site, and that further
excavation would jeopardize the building foundation. Therefore,
an in-situ remedial process utilizing a combination of bioremediation
and vacuum enhanced recovery was selected as the most cost-effective
remedial alternative. The basement was slab was replaced following
installation of the remedial equipment, and remedial goals
were achieved within four months.
Former Gas Station - Removal and disposal
of five (5) underground storage tanks and approximately 1,200
cubic yards of petroleum contaminated soils. Developed and
implemented a PA DEP approved site characterization plan.
Installed numerous mini-wells, test probes, and established
a groundwater monitoring network. Remedial activities consisted
of the application of oxygen release compounds to enhance
biodegradation and natural attenuation. Site was monitored
until eight quarters of compliant groundwater data was collected,
and closure obtained.
Operating Gas Station - Managed the site
characterization and remedial design for gas station with
leaking dispenser lines. Slug and falling head tests were
used to measure aquifer parameters at the monitoring wells.
Field mapping of joints, lineaments, and formation orientation
influenced the remedial design and explained the unique orientation
of the contaminant plume. The release affected 12 nearby residential
wells, and a citizens participation program was established
to provide the adjacent landowners with information and reports
about the ongoing project.
Operating Fuel Station - Conducted the
emergency response, site characterization, and remedial activities
at a site with several hundred gallons of free product released
in an area underlain by karst geology and controlled by a
large fault traversing the site. Installed a pump and treat
system to recover free product, but more importantly, to maintain
control of the contaminant plume. This project was particularly
interesting because of the heterogeneity of the limestone
aquifer (transmissivities measure in long-term pump tests
varied by an order of magnitude from 200 to 27,000 gpd/ft)
and the structural elements of the bedrock. Because of the
large fault dissecting the site, the contaminant plume was
dispersing in a direction normal to groundwater flow. The
aquifer was at a depth of 80 feet, and twenty-eight wells
were drilled to define the extent of contamination.
The geophysical method applied at the site consisted of
an EM34 ground conductivity survey conducted on a twenty-foot
grid initially. This survey showed a southward dipping monocline
with several sinkhole areas. A second survey was conducted
on a 10-foot grid. The 10-foot grid clearly delineated the
fault and was instrumental in explaining the orientation of
the plume, and arriving at a realistic fate and transport
model.
Demolished Factory with Hidden USTs –
A Phase I assessment of an open lot formerly containing a
trucking company warehouse. The distribution center had been
demolished, and the ground leveled. No prior drawings were
available for the site. An EM31
() ground conductivity survey was therefore conducted to search
for underground storage tanks. The survey detected an anomaly
that was then investigated with a test trench. The trench
encounterd two (2) leaking underground storage tanks. Remedial
activities included the removal of the leaking tanks, and
associated contaminated soils and liquids. The soil was approved
for out-of-state recycling and three monitoring wells were
installed on the property. A DICAR investigation completed,
and the State of New Jersey granted an approved closure after
two rounds of sampling. The wells were installed out of the
way of proposed development, which proceeded without delay.

|